TRANSFORMER

RTF date conversion

RTF (Relative to fixed) date conversion is used to adjust a date with the value of a field and by using the date calculator.

 

Creating an RTF date conversion process

To create an RTF date conversion process, right click in the Transformer design panel, choose Process -> RTF date conversion. Connect it to the previous process as described in Processes.

Properties

Name

 

Audit

 

Custom

 

The next three fields make up the basis for calculating the adjustment:

 

Examples:

The Start date is "January 1, 2017", the Interval is "Day", and the Adjustment function is "+EM".

 

If Source field contains the value "200" then 200 days will be added to the Start date January 1, 2000. That will give "July 20, 2017". Adjustment function = "+EM" will give "July 31, 2017".

 

Similarly, if the Source field contains 400 and the Adjustment function is +EM the result will be February 28, 2018.

 

 